Project details
Client: Mayfield Property Group
Services: Quantity Surveying
Value: £2.4 million (Phase 1)
Location: Bermondsey, London
Contract: JCT Design and Build 2016
Construction Period: 11 months

Talk to our experts
Project Overview
Demolition of two existing houses to allow construction of a nine-unit apartment block. Works involved a secant piled basement and reinforced concrete frame with traditional brickwork, external walls and modern fit-out.
Phase 1 of the development included enabling works to allow for a future cantilevered three-floor extension which would extend about the airspace of the neighbouring building, owned by the same developer.
Our Services
Pre-contract services included:
- Cost planning - comparison of feasibility studies for a standard build and a future-proofed frame to allow for extension of the building
- Preparing consultant appointment for the design team
- Tendering the works
- Negotiating with the selected contractor
- Compiling the contract, including collateral warranties
Post-contract services included:
- Monthly contractor valuations and funding drawdown applications
- Monthly cost reporting
- Chairing site meetings
- Assessing variations and contractor notices
- Agreeing the final account with the contractor
Want to find out more about our Disputes and Advisory services?
Read more Advisory news
News

SOCOTEC Advisory Training Suite and Services
Read +

Members of our Advisory team have been commended by Who’s Who Legal (WWL)
Read +

SOCOTEC UK Launches New Expert Search
Read +

SOCOTEC Opens London Hub
Read +

Base Quantum Rebrand as SOCOTEC Advisory Ltd
Read +